Pacific Energy delivers Australia’s largest off-grid hybrid system to power a mine

Pacific Energy says it has successfully completed a significant renewable energy expansion of its power system at the Tropicana gold mine in Western Australia.

The hybrid power system, delivered under a new 10-year build-own-operate agreement, commenced commercial operations on February 7, 2025.

The project, which adds 61 MW of renewable energy to Pacific Energy’s existing 54 MW gas-fired power station, brings the total capacity to 115 MW, making it Australia’s largest off-grid hybrid system to power a mine.

Tropicana is owned by AngloGold Ashanti Australia Ltd (70% and manager) and Regis Resources Ltd (30%), and is 330 km northeast of Kalgoorlie in Western Australia.

The renewables expansion incorporates four 6 MW wind turbines, a 24 MW solar farm and a 13 MW grid-forming battery energy storage system (BESS).

The integration of Pacific Energy’s cutting-edge intelligent control solution, BESS and virtual synchronous machine technologies means assets can work in harmony to stabilise the 115 MW system. This approach replaces legacy solutions like thermal-powered spinning reserve and synchronous condenser units, resulting in a state-of-the-art, technically advanced power system.

This combination of technologies also enables ultra-responsive hydrocarbons-off functionality, which can power Tropicana’s mining operations using 100% solar, wind and BESS for extended periods of time.

The new facility is expected to reduce Tropicana’s diesel and gas consumption for power generation by 96% and 50%, respectively, slashing carbon emissions by an average of 65,000 t/y over the life of the agreement, the company says.

Pacific Energy’s new wind-solar-battery facility will support AngloGold Ashanti’s strategy to reduce its global net carbon emissions from energy use by 30% by 2030, as part of its roadmap to achieve net zero carbon emissions by 2050. It is the first of its kind to be implemented within the AngloGold Ashanti group.

Pacific Energy’s Chief Executive, Jamie Cullen, said: “The new assets have already generated over 38,000 MWh of renewable energy, and that’s mostly while we were still bringing the equipment online. We’re also on track to displace an average of more than 1,100 TJ of gas with solar and wind generated power every year, and we expect to almost entirely displace diesel, which is now there purely for emergencies.

“In real-world terms, these fuel reductions will reduce Tropicana’s power generation emissions by upwards of 45%, which is equivalent to taking more than 14,000 cars off the road.”

Cullen said that, despite encountering some significant challenges, including severe flooding during the construction phase, the project was delivered safely, on time and on budget.

“Our Tropicana project involved more than 200,000 on-site labour hours, so it’s only through careful planning and our team’s collective commitment to safety best-practices that we’ve delivered this in a live mining operation with zero lost time injuries and zero medically treated injuries,” he said. “It’s something Pacific Energy and AngloGold Ashanti can be really proud of.

“AngloGold Ashanti trusted Pacific Energy to deliver an outcome that’s aligned with their net zero strategy and their commercial and operational goals. We’re really proud to have achieved exactly what we committed to back in 2023, and to have integrated cutting-edge technologies that will continue to support their decarbonisation pathway for years to come.”